Bus Garage & Salt Storage Relocation

Sign up for email Project Updates as we move forward with the construction of the salt storage facility and bus garage on Hudson Drive! 

Click here to receive updates.
Bus Garage
Salt Storage

Construction Update 6/8/18

The Hudson Salt Storage and Bus Maintenance Garage Facility Project is under way. This past week the contractor performed tree clearing, demolition of existing house and installation of 8” sanitary sewer along Hudson drive.  Next week’s work will include Back-filling of demo site, completion of sanitary sewer extension and stripping of topsoil.

If you have questions, contact the Hudson Engineering Department at 330-342-1770.
6-7-18 Clearing
6-5-18 demo

Project Description


In preparation for the Downtown Phase II Development Project, the City of Hudson's salt storage and Hudson School's Bus Garage Facility is being relocated. The project consists of constructing a new school bus garage and road salt storage structure on the City-owned parcel located at 5810 Hudson Drive, commonly referred to as the "Koberna property."

Preliminary Site Plan. Click photo for larger view.

Site Plan

Updates

February 26, 2018: Contract was awarded to Cavanaugh Building Corporation.

January 30, 2018: Bids were opened for the construction of the Salt Dome and Bus Garage.

January 16, 2018: Design is 100% complete.

November 21, 2017: The City entered into a wetland mitigation agreement with EnviroScience to develop a mitigation plan, manage the work through construction and monitor and modify the wetland mitigation site to ensure it reaches its intended goal.

June 25, 2017: Notice of Receipt of 401 Application

January 2017: Design is halfway complete.

September 26, 2016: 
The Planning Commission discussed Case 2016-23 on Monday, September 26, 2016 at 7:30 p.m. at Town Hall to discuss, a request from the City of Hudson for approval of a site plan for a salt storage structure and a school bus garage to be located on Hudson Drive. Planning Commission approved the conditional use of government facilities and the site plan for the new bus garage and salt storage facility.

September 12, 2016: Case 2016-23 was scheduled to be discussed at the September 12 Planning Commission meeting. The meeting was canceled and rescheduled for September 26.

August 16, 2016: The City selected the Environmental Design Group for the final design of the new salt storage facility and bus garage. Once the design is finished, we anticipate construction to be completed late next year.

June 21, 2016: The City of Hudson held a public information meeting for the adjacent property owners and interested residents on June 21, 2016. At that meeting, project staff provided a preliminary project time line, preliminary plans and exhibits. The majority of construction work will be completed in 2017 and 2018. For information provided at the meeting, please contact Christopher Papp, P.E., Assistant City Engineer at (330) 342-1770.

Current location of salt dome and bus garage.

HPP Bus Garage Cropped.jpg

Future location of salt dome and bus garage.

Koberna Property.jpg