Barlow Road Intersection, Railroad & Future Improvements

​Barlow Road and Terex Road Intersection



  • Where: Barlow Road and Terex Road (West) Intersection
  • When: March 20, 2017
  • Length: Approximately 4-5 months
The City of Hudson has entered into a contract with Signal Service Company (Bid Results) to construct a signal at the Barlow Road and Terex Road (West) intersection.

Signal Service Company started construction on March 20, 2017. The contractor is performing underground work for 2-3 weeks and then there will be a 3-4 month period of no work while the signal pole and arm are manufactured. Once equipment is available it will take another 2-3 weeks to finish the project. 

The traffic signal will include installation of the necessary underground infrastructure and the foundation for the signal pole. There is a single signal pole and arm for this location. Generally the work will occur off road and will not generally affect traffic.  If needed, traffic will be maintained with flaggers during the daytime construction operations. During the signal construction, access to your driveway may be limited for a short duration, as needed to complete the work.  If this occurs, the contractor will notify adjacent property owners in advance.

If you have any questions or comments, please do not hesitate to contact the Engineering Department at 330-342-1770 or via
email.
Barlow Road Future Map Final

Barlow Road at the Railroad Crossing: 



  • Where: Barlow Road at the Railroad Crossing
  • When: Beginning the week of April 3, 2017
  • Length: Up to 120 days
  • Completion:  Estimated mid-July, weather dependent

Construction Update:

The Contractor has finalized mass grading, storm sewer installation, curb and concrete driveway approach installation.  Landscape restoration is scheduled for the week of July 5.  Asphalt installation is scheduled for the week of July 17.  The roadway should be re-opened to traffic by the end of July.



Project Details:


The City of Hudson contracted with United Earthworks (Bid Results) to perform road profile improvements on Barlow Road at the railroad crossing. This project includes pavement removal, fill construction, asphalt pavement, curb, storm and utility work, pond removal, signage and pavement markings.

In order to compete the project, Barlow Road is closed at the railroad tracks for up to 120 days. Detour signage is in place.

If you have any questions or comments, please do not hesitate to contact Brad Kosco, PE, PS, Assistant City Engineer, at 330-342-1770 or bkosco@hudson.oh.us.


Multi-Purpose Trail

Anticipated construction 2018
  • Part of the citywide connectivity plan.
  • A sidewalk & multi-purpose path is being designed along Barlow Rd from SR 91 to Terex Rd (W).
  • The path will connect to the Summit County Metro Bike Pathway.
  • More information will be provided once the design is developed over the next year.