Barlow Road Railroad & Future Improvements

Barlow Road Future Map Final

Railroad Crossing

Winter 2016-Spring 2017
  • 11/16/16 Bid Results

  • 10/23/16 Advertisement for Bids
  • Make the railroad crossing safer.

  • Raise the slope of the roadway at the railroad tracks.

  • Reconstruct the grade of Barlow Road near the railroad tracks (500' each side of the railroad crossing).

  • Correct alignment of Barlow Road.

  • Barlow Road will be closed at the RR tracks for 45-60 days.

  • Summit County Metro is currently reviewing plans.

  • Anticipate bidding the project late, 2016.

Traffic Signal Installation

Anticipated Spring 2017
  • Traffic signal installation at the intersection of Barlow & Terex Rd (W).
  • The signal will be operational by late, 2017.
  • Plans are expected to be completed in the next 6 months.

Multi-Purpose Trail

Anticipated construction 2018
  • Part of the citywide connectivity plan.
  • A sidewalk & multi-purpose path is being designed along Barlow Rd from SR 91 to Terex Rd (W).
  • The path will connect to the Summit County Metro Bike Pathway.
  • More information will be provided once the design is developed over the next year.