SR 91 North Turn Lane Improvements (PID 93822)

Want to receive email updates about this project? SIGN UP HERE or view project updates below.

Project Description



What

The SR 91 North Turn Lane Improvements project includes:
  • The addition of left turn lanes at Valley View Road, Herrick Park Drive, and Hines Hill Road
  • The installation of an 8-foot sidewalk and curb on the east side of the roadway
  • The installation of 5-foot bike lanes on both sides of the road
  • Resurfacing of SR 91 from Brandywine Drive to Middleton Road
  • Improved intersection lighting
  • The elimination of heaving shoulders along both sides of the roadway
  • Improved drainage systems
  • The City of Akron Water will install a new waterline between Herrick Park Drive and Middleton Road.
The final project plans can be viewed here. Please note the large file size (72 mb) and allow time to download

.


Where

SR 91 between Brandywine Drive and Middleton Road.

Why

The purpose of this project is to improve safety, reduce congestion, provide better pedestrian and bicycle mobility, improve drainage, and improve long-term pavement conditions on SR 91 between Brandywine and Middleton Road.

When

The project construction is anticipated to last two construction seasons and finish in the summer of 2021.

Impacts

The contractor will be required to maintain two-way traffic along SR 91 at all times during construction, but delays can be expected.

Contact Us

Should you have any questions or comments, please contact:
Nate Wonsick, P.E.
Assistant City Engineer
Phone: 330-342-1776
Email

Project Limits

SR 91 N Rotated
  1. Project Update 6/17/2021

    Over the past two weeks the contractor has been working on sidewalk and driveway installation, underdrains, mailbox posts, ada ramps, pavement removals, and electric. Read on...
  2. Hines Hill Road Closure Will Begin Monday for 30 Days

    As part of the SR 91 N. Turn Lane project, Hines Hill Rd. will be closed right off of SR 91 for 30 days beginning on Monday, June 21. During the closure, 100 feet of the roadway will be reconstructed. Detours will be posted. Read on...
  3. Project Update 5/21/2021

    Over the past two weeks the contractor has been working on grading for curb and installing curb, began sidewalk install, and started work on turnpike bridge walls. Read on...