The bridge on SR 91/Darrow Road over the bike trail has been replaced with an arch culvert. Darrow Road now has two lanes, northbound and southbound, and a left turn lane for southbound traffic at Fishcreek Road. Fishcreek Road has been reconstructed with new curbs and a future turn lane to southbound Darrow Road. Construction work will continue on both roadways which will require temporary lane restrictions.
Storm sewer work on Norton Road, signalization of the Fishcreek Road/Darrow Road intersection, and a partial opening of the bike trail will occur in December. Details about the December work can be found here.
The City of Stow Engineering Department is the lead agency for this project. Questions? Call the Stow Engineering Department at 330-689-2719 or email Jim McCleary.