SR 91 North Turn Lane Improvement Project

Posted on: September 25, 2020

Project Update 9/25/2020

SR 91 Turn Lane Project Update

Over the past two weeks the contractor has completed the installation of 8 inch water line at the south end of the project, installed bore pits for upcoming 16 inch water main work, completed minor grading, and started saw cutting the pavement. Over the next two weeks the contractor will be setting steel reinforcement and formwork for culvert headwall installations, continuing pavement saw cutting, and starting installation of 16 inch water main.

Facebook Twitter Email

Other News in SR 91 North Turn Lane Improvement Project

SR 91 Turn Lane Project Update

Project Update 11/20/2020

Posted on: November 23, 2020
SR 91 Turn Lane Project Update

Project Update 11/5/2020

Posted on: November 5, 2020
SR 91 Turn Lane Project Update

Project Update 10/23/2020

Posted on: October 23, 2020
SR 91 Turn Lane Project Update

Project Update 10/9/2020

Posted on: October 9, 2020
sr 91

Project Update 9/15/20

Posted on: September 15, 2020
SR 91 Turn Lane Project Update

SR 91 Turn Lane Project Underway

Posted on: September 2, 2020
SR 91 Turn Lane Project Update

Project Update 6/4/2020

Posted on: August 31, 2020
SR 91 Turn Lane Project Update

Project Update 3/9/2020

Posted on: August 31, 2020
SR 91 Turn Lane Project Update

Project Update 3/2/2020

Posted on: August 31, 2020
SR 91 Turn Lane Project Update

Project Update 1/23/2020

Posted on: August 31, 2020
SR 91 Turn Lane Project Update

Project Update 4/19/2019

Posted on: August 31, 2020