Over the past two weeks the contractor has continued to work on the installation of 16 inch water line at the north end of the project, including installation of fire hydrants. The testing and chlorination of the 8” water line at the south end of the project and pavement saw cutting was also completed. Over the next two weeks the contractor will be continuing to install the 16 inch water line and may start culvert headwall installations.