Over the past two weeks the contractor has installed drainage/storm sewer work along entire project corridor. Waterline items have been completed except for two service connections. Over the next two weeks the contractor will be installing storm sewer crossings along the west side of SR 91, Valley View/Hines Hill storm sewer work, storm headwall installation, and grubbing and ditching on west side of 91.