Over the past two weeks the contractor has installed drainage/ storm sewer work along entire project corridor and installed 2 waterline services. All waterline items have now been completed. Over the next two weeks the contractor will be continuing with drainage/ storm sewer work along entire project corridor including storm sewer headwall installation.